Midway ISD’s investment in student learning spaces and reliable facilities continues to take shape, with high school construction on schedule, campus improvements planned during upcoming breaks and renovations proposed to repurpose the former DAEP building.

The Board of Trustees received an informational update on bond projects at its regular November meeting, highlighting construction milestones and upcoming work across the district.
At Midway High School, grade beams are complete and underground plumbing is approximately 70% complete. Electrical conduit installation is scheduled for Nov. 23, followed by the first slab pour Dec. 1. Structural masonry work is scheduled to begin Dec. 14.
“It is exciting to see our community’s investment taking shape,” Midway ISD Director of Operations Ken Wolf said. “These projects support the spaces where students learn, prepare and participate in the programs that make their Midway experience what it is.”
The district is also preparing to renovate the former Disciplinary Alternative Education Program building for use by the Special Populations Department. The project combines repairs following June flood damage with improvements to adapt the existing building for its new purpose.
The estimated $220,635 project includes approximately $103,385 in insurance-funded flood repairs, including interior walls, flooring and cabinetry. Approximately $117,250 in 2025 bond funds would support office construction, lighting, ceiling, HVAC and electrical improvements, along with exterior repairs and sealing.
A separate November agenda item requested approval of a purchasing cooperative procurement method and authorization for expenditures not to exceed $225,000.
Other facility improvements are scheduled around upcoming school breaks. At Castleman Creek Elementary, heating and air-conditioning work in offices and classrooms is planned over Thanksgiving and winter breaks. Once finished, the project will complete the campus HVAC update.
River Valley Middle School is scheduled to receive replacement drinking fountains over Thanksgiving break. At the Administration Building, a generator installation and electrical upgrades supporting technology systems are tentatively planned for winter break, with timing dependent on equipment delivery.
“Taking care of our existing buildings is an important part of protecting our community’s investment,” Superintendent Dr. Chris Allen said. “These projects allow us to extend the life of our facilities, put available space to good use and support the people serving our students.”
Together, the projects advance new construction and maintain the dependable facilities that support Midway’s students and staff.